Discovery
We begin by understanding your vision. In this first meeting, we will establish the following -
Key Documents & Approvals

Scope of Work

Your Design Preferences

Planning
Based on your requirements, we prepare the following
Architectural Plans

Structural Plans

Design
Specifications

Detailed Cost Estimation

2 Weeks
Clarity in brief & design preferences produces a more accurate estimate
Preparation
Before we start constructing, we do the following in preparation
Centerline Drawing

Used to mark the plan on the site
Earthwork

Begins after the site markings are approved
Site Set-up

Protective fencing & Sanitation for workers
Foundation & Structure
We take every step needed to build a sturdy, long-lasting skeleton
Earth Excavation & Pest Control

Before PCC
PCC / Raft Foundation

The first layer - a bed of concrete that acts as a moisture barrier
Sump Construction

-
Column Footing & Isolated Column Work

-
Columns

-
Grade Beam Casting

-
Earth Filling

-
Pest Control & Floor PCC

-
Columns

Upto the roof level
Staircase Work

Upto the first floor
Roof Slab

Centering, bar bending & concreting
Upper Floors

The process repeats for the upper floors
Brickwork & Finishing
Once the shell is done, we start on everything in-between
Brickwork

After slab deshuttering
Sill slabs, Lintels & Sunshades

Installed
Door Frame

Fixed
Electrical Conduits & Switch Boxes

Fitted
Chicken Mesh

Applied to beam / brick joints to prevent cracks
Internal Plastering

After electrical and frameworks
Putty & Base Painting

2 coats of putty on the wall
Plumbing & Waterproofing
Kitchens, bathrooms and other water prone areas are made leak-proof
Plumbing Lines

Laid in bathrooms and kitchens
Floor Waterproofing

Before the tiles are laid
Drainage Piping

Floor drain piping completed & pressure tested
Terrace Waterproofing

Before the weathering course
Flooring & Roofing
From the floor, to the ceiling - we've got you covered
Tile, Marble or Granite

Laid as per the design
Terrace Weathering Course

Applied with thermal / pressed tiles
Rainwater Pipes

Installed
Parapet Wall

Finished with sill slab for crack protection
External Works
We then focus on building a safe and aesthetic compound
Compound Wall

-
Landscaping

-
Gate

Grill fabrication & installation
Final Fixes & Handover
We make sure everything is ready for use before handover
Fittings

Electrical fittings, light fixtures & air conditioners
Paint

One coat of finishing paint
Snag List

Installed